Details of 2002 ReCharge


Work Schedule - Summer 2002

· Work will be carried out weather permitting
o 24 hours a day
o 7 days a week
o from mid April until September

· All activities are tide dependent

Activity Approx. Timings Duration
Shingle Delivery (by dredger) -1 hour ® High Water ® +1 hour 2 hours
Shingle Retrieval - BY DAY -3 hour ® Low Water ® +3 hour 6 hours
Shingle Retrieval -BY NIGHT EARLY 3 hour ® Low Water 3 hours
Or
Or
 
Shingle Retrieval -BY NIGHT LATE Low Water ® +3 hour 3 hours

Beach work in the middle of the night has to be done to retrieve deposited shingle. Whenever possible this will be kept to a minimum, with any necessary profiling done during daylight hours

Each groyne bay being replenished will be fenced off during operations

A Westminster Dredging "Beach Master" will be in attendance at all times when either shingle is being delivered or retrieved

Area Approx. Locations Approx. Duration
Beachlands 400 to 464 Coast Road Mid April - Mid June
Normans Bay West Seaward of all properties June - Early July
Normans Bay East Seaward of all properties July - Early August
Herbrand Walk East Stream Outfall to Beach Huts August - September