Work Schedule - Summer 2002
· Work will be carried out weather permitting
o 24 hours a day
o 7 days a week
o from mid April until September
· All activities are tide dependent
Activity Approx. Timings Duration Shingle Delivery (by dredger) -1 hour ® High Water ® +1 hour 2 hours Shingle Retrieval - BY DAY -3 hour ® Low Water ® +3 hour 6 hours Shingle Retrieval -BY NIGHT EARLY 3 hour ® Low Water 3 hours Or OrShingle Retrieval -BY NIGHT LATE Low Water ® +3 hour 3 hours
Beach work in the middle of the night has to be done to retrieve deposited shingle. Whenever possible this will be kept to a minimum, with any necessary profiling done during daylight hours
Each groyne bay being replenished will be fenced off during operations
A Westminster Dredging "Beach Master" will be in attendance at all times when either shingle is being delivered or retrieved
| Area | Approx. Locations | Approx. Duration |
| Beachlands | 400 to 464 Coast Road | Mid April - Mid June |
| Normans Bay West | Seaward of all properties | June - Early July |
| Normans Bay East | Seaward of all properties | July - Early August |
| Herbrand Walk | East Stream Outfall to Beach Huts | August - September |