Further to Wednesdays message, we are now reaching the conclusion of
work at Beachlands. Sospan Dau will deliver final loads at noon and midnight
today, before returning to Sovereign Harbour for two further loads. These will
be deposited on the 00:50 and 13:10 high tides on Monday.
Shingle will be recovered from the foreshore not before 07:30 on Monday morning
and again that evening. The cliffing already evident in the material already
placed will also be removed. Thereafter the bulldozer will be retained for the
forthcoming autumn and winter to help keep as much of the new material in place
as possible and to remove further cliffing as it appears.
If you have any queries or comment please dont hesitate to contact me.
Best wishes
Ian