2008 Beach - News - 7th April


With no windy weather predicted for the next few days, the final three high tides of spring are not expected to create any problems. All machines moving shingle left the beach on Friday, and with luck will not need to return until the autumn. One bulldozer remains to remove ruts from the beach crest and generally re-grade disturbed areas. This should finish early next week. Two men will be going along the beach on the early morning low tide this week removing any loose or protruding groyne parts. These may be piled at the top of the beach for a couple of days before being collected by a small dumper.

Hopefully there will be a long and pleasant summer to enjoy before it all starts again in the autumn.

Best wishes

Ian

Ian Thomas
Project Manager
Pevensey Coastal Defence Ltd
Environment Agency Depot