December 2007 was certainly better than the same period in 2006, although there
have been several stormy periods. As a result some shingle needs to be moved
in order to maintain the same standard of defence throughout the Bay. Firstly,
shingle will be transferred from Langney, round Sovereign Harbour, and on to
the beach to the east using Pacific Drive. This will start on Monday 7th January
and be finished on either Thursday 10th or Friday 11th. Monday 14th will see
the beginning of a short two-week recycle, with 2-3 days work at each of; the
Harbour, Beachlands, Normans Bay East and Cooden/Herbrand Walk. Any change in
weather patterns could mean a change to this programme, but updates will be
provided as events unfold.
Full details are also available on the website at http://www.pevensey-bay.co.uk/news.html
Best wishes
Ian
Ian Thomas
Project Manager
Pevensey Coastal Defence Ltd
Environment Agency Depot
Coast Road
Pevensey Bay
East Sussex BN24 6ND
Tel: 01323 761202
Fax: 01323 764368
Mob: 07884 234298
email: pcdl@pevensey-bay.co.uk