With main school holidays to start at the end of this week, we decided to get
as much of the remaining work out of the way as possible in the next five days.
A final shingle transfer round the harbour started this morning and will continue
all week. The small heap of shingle temporarily stored on the beach behind the
Langney Martello tower will be removed during that time.
A final few days of recycling will concentrate on Normans Bay East, Beachlands
and Sovereign Harbour in that order. Work will start at Beachlands on Wednesday
with the final three days split between there and the harbour.
The one activity that will take place next week is that of a small gang going
along the beach and checking groynes for loose and unsafe pieces, which they
will remove. By necessity this has to be done at low water, and with spring
tides over the early part of the week it will maximise the area that can be
covered
The 6-10 day forecast currently shows cooler showery weather, so it is hoped
this final high spring tide will come and go without any undue alarms.
Best wishes
Ian
Ian Thomas
Project Manager
Pevensey Coastal Defence Ltd
Environment Agency Depot
Coast Road
Pevensey Bay
East Sussex BN24 6ND
Tel: 01323 761202
Fax: 01323 764368
Mob: 07884 234298
email: pcdl@pevensey-bay.co.uk